The 18 everyday calculations of water treatment: laboratory, biological process, membranes, dosing and disinfection. Each calculator shows its formula and offers practice problems.

Laboratory

Suspended solids (TSS / VSS)

FormulaTSS = (B − A) × 10⁶ ÷ V  ·  VSS = (B − C) × 10⁶ ÷ V
g
g
g
mL
TSS—mg/L
VSS—mg/L
VSS / TSS—%

Mixed liquor: 10 to 25 mL; effluent: 100 to 1000 mL. Typical VSS/TSS: 65 to 85 %.

Sludge volume index (SVI)

FormulaSVI = SV₃₀ × 1000 ÷ X
mL/L
mg/L
SVI—mL/g

Typical: 80 to 150 mL/g. Above 150 the sludge settles poorly (possible filaments). If SV₃₀ is over 800 mL/L, dilute the sample and multiply by the dilution.

Total alkalinity (titration)

FormulaAlk = (Vₐ − Vb) × N × 50 000 ÷ Vs  (mg/L CaCO₃)
mL
mL
N
mL
Alkalinity—mg/L CaCO₃

Titrate to pH 4.5. To nitrify, keep at least 50 to 70 mg/L CaCO₃ in the tank.

Diluted sample

FormulaF = (Vs + Vw) ÷ Vs  ·  result = reading × F
mL
mL
mg/L
Dilution factor—×
Actual result—mg/L
If PO₄: as P (× 0.326)—mg/L

The reading must fall inside the test range; if not, dilute further and repeat.

Biological process

Removal efficiency

FormulaE = (Cᵢ − Cₑ) ÷ Cᵢ × 100
mg/L
mg/L
Removal—%

Works for BOD, COD, TSS, ammonia or phosphorus: same parameter in and out.

F/M ratio (food to microorganisms)

FormulaF/M = Q × DBO₅ ÷ (V × MLVSS)
m³/d
mg/L
m³
mg/L
F/M—kg BOD/kg MLVSS·d

Conventional activated sludge: 0.2 to 0.5; extended aeration and membrane bioreactors: 0.05 to 0.15.

Sludge age (SRT)

FormulaSRT = V × X ÷ (Qw × Xw + Q × Xe)
m³
mg/L
m³/d
mg/L
m³/d
mg/L
Sludge age—d

Conventional: 5 to 15 d; to nitrify, more than 8 to 10 d depending on temperature; membrane bioreactors: 15 to 30 d.

Wasting rate for a target sludge age

FormulaQw = (V × X ÷ SRT − Q × Xe) ÷ Xw
m³
mg/L
d
mg/L
m³/d
mg/L
Sludge to remove—kg/d
Waste sludge flow (Qw)—m³/d

Change wasting in small steps (10 to 15 % per day) and watch the MLSS trend before adjusting again.

Hydraulic retention time (HRT)

FormulaHRT = V ÷ Q × 24
m³
m³/d
Retention time—h

Use the volume actually in service (real tank level) and the day's average flow.

Return sludge ratio (RAS)

FormulaR = Qr ÷ Q  ·  R* = X ÷ (Xr − X)
m³/d
m³/d
mg/L
mg/L
Current ratio (R)—
Ratio required by mass balance (R*)—

If the current ratio is lower than the required one, sludge builds up in the clarifier.

Organic load

Formulaload = Q × C ÷ 1000  ·  Bv = load ÷ V
m³/d
mg/L
m³
Daily load—kg/d
Volumetric load (Bv)—kg/m³·d

Compare the daily load with the plant's design load: that is what tells you whether the process is being pushed.

Observed yield (sludge production)

FormulaYobs = W ÷ (Q × (Cᵢ − Cₑ) ÷ 1000)
kg TSS/d
m³/d
mg/L
mg/L
Observed yield—kg TSS/kg BOD

Typical: 0.4 to 0.8; lower when the sludge age is high.

Oxygen uptake rate (OUR / SOUR)

FormulaOUR = (OD₀ − OD₁) ÷ t × 60  ·  SOUR = OUR ÷ MLVSS
mg/L
mg/L
min
g/L
OUR—mg O₂/L·h
SOUR—mg O₂/g VSS·h

Typical SOUR: 8 to 20. Very low: inhibited or under-fed biomass; very high: overload.

Nitrification: oxygen and alkalinity

FormulaO₂ = (Nᵢ − Nₑ) × Q × 4,57 ÷ 1000  ·  Alk = (Nᵢ − Nₑ) × Q × 7,14 ÷ 1000
mg/L
mg/L
m³/d
Oxygen required—kg O₂/d
Alkalinity consumed—kg CaCO₃/d

Denitrification gives back about half of the alkalinity consumed. If alkalinity runs short, nitrification stops and the pH drops.

Membranes

Flux and permeability (corrected to 20 °C)

FormulaJ = Qp × 1000 ÷ A  ·  K₂₀ = J ÷ (PTM ÷ 100) × 1,024(20 − T)
m³/h
m²
kPa
°C
Flux (J)—L/m²·h
Permeability at 20 °C (K₂₀)—L/m²·h·bar

Follow the K₂₀ trend rather than a single value: a 20 to 30 % drop signals fouling. Clean as the manufacturer's procedure says.

Chemical dosing and disinfection

Chemical feed: mass and pump rate

Formulakg/d = Q × D ÷ 1000  ·  L/h = kg/d ÷ (C% ÷ 100 × ρ) ÷ 24
m³/d
mg/L
% m/m
kg/L
Active product—kg/d
Pump rate—L/h
Pump rate—mL/min

Dose and strength must be on the same basis (active product). A dosing pump's real output is confirmed with a calibration test.

Alum for phosphorus removal

FormulaAl = (Pᵢ − Pₑ) × r  ·  alun = Al × 11  (Al₂(SO₄)₃·14H₂O)
mg/L
mg/L
g/g
m³/d
Aluminium—mg/L
Dry alum—mg/L
Dry alum per day—kg/d

Common starting point: Al:P ratio of 1.5 to 2.5. Then adjust with jar tests and effluent P results. Too much alum eats alkalinity.

Chlorination: dose, demand and CT

Formulademand = dose − residual  ·  kg/d = Q × dose ÷ 1000  ·  CT = residual × t₁₀
m³/d
mg/L
mg/L
min
Chlorine demand—mg/L
Chlorine per day—kg/d
CT—mg·min/L

The CT required depends on the target organism, pH and temperature: compare with the regulatory tables that apply to your plant.

Learning and checking tools. The ranges shown are general guidance: always follow your plant's procedures, permits and set points. Nothing is sent anywhere: the calculations run in your browser.

Practise on a virtual plant ↗

The same maths, with a plant that reacts: the Beedy simulators.